Service Training
Page 4.2
Section 71
09.04
noyes
K
noyes
noyes
Install LP gauge with adapter III to ports YF and ZF of power limiter. Repeat the
test.
I
noyes
L
M
Δp 0 - 0,5 bar.
Δp now 0 - 0,5 bar.
Δp 0 - 0,5 bar.
Check or renew travel
control unit.
Equal pressure
can be achieved.
Check for equal pressure, see "Pressure equality and start of control".
Remove adapter III and install adapter II with plug. Connect LP gauge and
determine Δp with the brake released and engine running.
Leak in hydraulic remote
control. Repair or renew
the remote control.
Power limiter defective
(nozzles in ports YF/ZF
maybe clogged).